Progress Plan for Construction Phase 1 – Including Noise Indicator
Approx. 19–30 May 2025:
-
Installation of contractor facilities (offices, locker rooms, dining areas) southwest of Krona
-
Fencing of the construction site
2 June 2025:
-
All cars and motorcycles must be removed from the area
Approx. 2–27 June 2025:
-
Excavation of the site west of Inferno, Jubilo, Grotten, and Hemsen
-
Blasting operations – noise should be expected
June 19: Start of pipe drilling for the pipe wall. Note: Noise should be expected.
Weeks 26–28: Pipe drilling for the pipe wall continues, and excavation for houses 14 and 16 will begin towards the end of the period. Note: Noise should be expected, including on Saturdays between 7:00 AM and 7:30 PM.
July–August 2025:
-
Work expected to be completed by week 32 (no later than week 34)
-
Securing of construction pit with steel pipe piling and drilling
-
Piling to bedrock
-
Work scheduled Monday through Saturday, 7:00–17:00
-
Intermittent periods of heavy noise are expected
September 2025 – February 2026:
-
Basement construction
March 2026 – May 2026:
-
Assembly of cross-laminated timber (CLT) structures
-
All four buildings will be erected and roofed
June 2026 – May 2027:
-
Interior work
June 2027:
-
Landscaping and outdoor area development
July 2027:
-
Move-in