Approx. 19–30 May 2025:

  • Installation of contractor facilities (offices, locker rooms, dining areas) southwest of Krona

  • Fencing of the construction site

2 June 2025:

  • All cars and motorcycles must be removed from the area

Approx. 2–27 June 2025:

  • Excavation of the site west of Inferno, Jubilo, Grotten, and Hemsen

  • Blasting operations – noise should be expected

June 19: Start of pipe drilling for the pipe wall. Note: Noise should be expected.

Weeks 26–28: Pipe drilling for the pipe wall continues, and excavation for houses 14 and 16 will begin towards the end of the period. Note: Noise should be expected, including on Saturdays between 7:00 AM and 7:30 PM.

July–August 2025:

  • Work expected to be completed by week 32 (no later than week 34)

  • Securing of construction pit with steel pipe piling and drilling

  • Piling to bedrock

  • Work scheduled Monday through Saturday, 7:00–17:00

  • Intermittent periods of heavy noise are expected

September 2025 – February 2026:

  • Basement construction

March 2026 – May 2026:

  • Assembly of cross-laminated timber (CLT) structures

  • All four buildings will be erected and roofed

June 2026 – May 2027:

  • Interior work

June 2027:

  • Landscaping and outdoor area development

July 2027:

  • Move-in

Do you have questions, encountered any issues, or would you like to give feedback related to the construction process at Pentagon? Feel free to reach out – we’ll follow up as soon as possible.